COUNTY: DeKalb |
DATE: November 8, 2012 |
|
|
|
|
|
|
|
|
|
|
|
|
TOWNSHIP: |
Cortland |
|
|
NAME AND ADDRESS |
|
Alliance Contractors,
Inc. |
|
Albin Carlson & Co.,
Inc |
Civil Constructors, Inc |
SECTION: |
12-03128-02-BR |
|
|
OF |
|
1166 Lake Avenue |
|
745 S. Rohlwing Road |
P.O. Box 750 |
|
ESTIMATE: |
$
232,590.00 |
|
|
BIDDERS |
|
Woodstock, IL 60098 |
|
Addison, IL 60101 |
Freeport, IL 61032 |
|
|
|
|
|
|
PROPOSAL
GUARANTEE: |
|
|
APPROVED |
|
|
|
|
|
ENGINEER'S |
|
TERMS: |
|
|
|
ESTIMATE |
|
Bid Bond: |
|
Bid Bond: |
Yes |
Bid Bond: |
|
Bid Bond: |
|
|
|
|
|
ITEM NO. |
ITEMS |
UNIT |
QUANTITY |
UNIT |
|
UNIT |
|
UNIT |
|
UNIT |
|
UNIT |
|
OR GROUP |
|
|
PRICE |
TOTAL |
PRICE |
TOTAL |
PRICE |
TOTAL |
PRICE |
TOTAL |
PRICE |
TOTAL |
|
|
|
|
1 |
Earth Excavation |
CuYd |
183.00 |
$ 25.00 |
$
4,575.00 |
$ 5.00 |
$
915.00 |
|
|
$ 48.00 |
$
8,784.00 |
$ 44.00 |
$
8,052.00 |
2 |
Removal of Existing Structure |
Each |
1.00 |
$ 35,000.00 |
$
35,000.00 |
$ 78,500.00 |
$
78,500.00 |
|
|
$ 56,000.00 |
$
56,000.00 |
$ 39,000.00 |
$
39,000.00 |
3 |
Precast,
Prestressed Concrete Deck |
SqFt |
2,138.00 |
$ 70.00 |
$
149,660.00 |
$ 51.50 |
$
110,107.00 |
|
|
$ 41.00 |
$
87,658.00 |
$ 52.00 |
$ 111,176.00 |
4 |
Beams (17"
Depth) |
|
|
|
$ - |
|
$ - |
|
|
|
$ - |
|
$ - |
5 |
Name Plates |
Each |
1.00 |
$ 450.00 |
$
450.00 |
$ 500.00 |
$
500.00 |
|
|
$ 535.00 |
$
535.00 |
$ 650.00 |
$
650.00 |
6 |
Steel Railing, Type S-1 |
Foot |
156.00 |
$ 120.00 |
$
18,720.00 |
$ 100.00 |
$
15,600.00 |
|
|
$ 99.00 |
$
15,444.00 |
$ 97.00 |
$
15,132.00 |
7 |
Aggregate Base Course,
Type B |
Ton |
42.00 |
$ 45.00 |
$
1,890.00 |
$ 20.00 |
$
840.00 |
|
|
$ 31.00 |
$
1,302.00 |
$ 77.00 |
$
3,234.00 |
8 |
Waterproofing Membrane System |
SqYd |
238.00 |
$ 30.00 |
$
7,140.00 |
$ 45.00 |
$
10,710.00 |
|
|
$ 45.00 |
$
10,710.00 |
$ 45.00 |
$
10,710.00 |
9 |
Bituminous Materials, Prime Coat |
Gal |
105.00 |
$ 4.00 |
$
420.00 |
$ 5.00 |
$
525.00 |
|
|
$ 5.00 |
$
525.00 |
$ 5.00 |
$
525.00 |
10 |
Hot-Mix Asphalt-Surface Cse, Mix C, N30 |
Ton |
51.00 |
$ 95.00 |
$
4,845.00 |
$ 165.00 |
$
8,415.00 |
|
|
$ 165.00 |
$
8,415.00 |
$ 165.00 |
$
8,415.00 |
11 |
Porous Granular Backfill |
CuYd |
150.00 |
$ 50.00 |
$
7,500.00 |
$ 20.00 |
$
3,000.00 |
|
|
$ 43.00 |
$
6,450.00 |
$ 68.00 |
$
10,200.00 |
12 |
Portland Cement Mortar Fairing Course |
Foot |
540.00 |
$ 3.50 |
$
1,890.00 |
$ 10.00 |
$
5,400.00 |
|
|
$ 1.00 |
$
540.00 |
$ 0.01 |
$ 5.40 |
13 |
Seeding, Class 2 (Special) |
Acre |
0.10 |
$ 5,000.00 |
$
500.00 |
$ 10,000.00 |
$
1,000.00 |
|
|
$ 15,000.00 |
$
1,500.00 |
$ 10,000.00 |
$
1,000.00 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
$
232,590.00 |
|
$
235,512.00 |
|
$
- |
|
$
197,863.00 |
|
$
208,099.40 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|