Waterman Road Project
Road Name: |
Waterman Road |
|
Road District |
Afton/Clinton |
|
Location: |
Perry Road to Duffy Road
|
|
Anticipated Start Date:
|
June 5, 2017 |
|
Anticipated Completion Date:
|
August 18, 2017 |
|
Contractor:
|
Civil Constructors, Inc., Freeport, Illinois
|
|
Contract Value:
|
$1,437,252.35
|
|
Improvements:
|
Rehabilitating 5 miles of Waterman Road but grinding existing surface, cracking underlying concrete, placing 6" of new aggregate surface course, placing a new Bituminous Surface Treatment (A-3) Seal Coat surface and other incidental work to include replacing cross road culverts and installing drain tile
|
|
Traffic:
|
Road will be closed to thru traffic – opened to local residents only |
|
|
PROGRESS UPDATES
(Please Remember to Refresh This Page for the Latest Update):
|
|
|
Date: |
Topic: |
|
May 24, 2017
|
Update Notice to Property Owners
|
|
June 1, 2017 |
Notice of Road Closing
|
|
June 2, 2017 |
Contractor to begin on Monday June 5, 2017
|
|
August 17, 2017 |
Mailbox Letter
|
|
August 25, 2017 |
Daily Construction Updates
|
|
Read more about past construction projects on the archives page
|