Waterman Road Project

 

Road Name:

Waterman Road

 

Road District

Afton/Clinton

 

Location:

Perry Road to Duffy Road

 

Anticipated Start Date:

June 5, 2017

 

Anticipated Completion Date:

August 18, 2017

 

Contractor:

Civil Constructors, Inc., Freeport, Illinois

 

Contract Value:

$1,437,252.35

 

Improvements:

Rehabilitating 5 miles of Waterman Road but grinding existing surface, cracking underlying concrete, placing 6" of new aggregate surface course, placing a new Bituminous Surface Treatment (A-3) Seal Coat surface and other incidental work to include replacing cross road culverts and installing drain tile

 

Traffic:

Road will be closed to thru traffic – opened to local residents only

 
  PROGRESS UPDATES  
(Please Remember to Refresh This Page for the Latest Update):

   

Date:

Topic:

 

May 24, 2017

Update Notice to Property Owners

 

June 1, 2017

Notice of Road Closing

 

June 2, 2017

Contractor to begin on Monday June 5, 2017

 

August 17, 2017

Mailbox Letter

 

August 25, 2017

Daily Construction Updates

 

 