County Bridge Projects
Road Name: |
Somonauk Road Bridge |
Road District: |
N/A |
Location: |
Bridge 0.25 miles South of US Route 30 in Hinckley, IL over Little Rock Creek |
Anticipated Start Date: |
May 21, 2018 |
Anticipated Completion Date: |
All major work to be completed by 4:00pm August 31, 2018 to allow for road opening; Minor items are to be completed by 4:00pm, September 21, 2018 |
Road Open to Traffic: |
NLT 4:00pm, August 31, 2018 |
Contractor: |
Civil Constructors, Inc., Freeport, Illinois |
Contract Value: |
$993,826.37 |
Improvements: |
Removal and replacement of existing three span slab bridge with a new single span concrete deck on steel beams with integral abutments bridge along with necessary roadway approach work |
Traffic: |
Road to remain closed during construction |
|
PROGRESS UPDATES:
|
|
|
|
(Please Remember to Refresh This Page for the Latest Update)
|
|
|
Date: |
Topic: |
|
August 31, 2018 |
Weekly Update -.PDF
|
|
Progress Photos: Select the photos to see larger images
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Application of pavement maring
|
Striping of new realigned roadway
|
Ditch stabilization underway
|
|
|
|
|
|
|
|
|
|
|
|
|
Guardrail being installed
|
Preparing to install guardrail
|
Aggregate Shoulders being placed
|
|
Surface Course being placed
|
|
|
|
|
|
|
|
|
|
|
Bridge rail being installed
|
Leveling binder being placed
|
Leveling binder being placed
|
|
Prime applied to realigned roadway
|
|
|
|
|
|
|
|
|
|
|
Covering deck to allow it to cure to obtain proper strength
|
|
Rebar in place ready for deck pour
|
|
Tying rebar prior to deck pour
|
|
|
|
|
|
|
|
|
|
|
|
|
Realignment of roadway continues
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Steel beams arriving at site
|
|
Abutments completed
and forms stripped
|
|
July 2, 2018
|
June 29, 2018
|
|
June 29, 2018
|
|
|
|
|
|
Preparing the base for new
alignment of Somonauk Road
|
|
Pouring of the Caps with concrete
|
|
Pouring of the Caps with concrete
|
|
June 25, 2018
|
June 20, 2018
|
|
June 18, 2018
|
|
|
|
|
|
Reshaping Somonauk Road for
better alignment to the bridge
|
Filling the piles with concrete after rebar has been set
|
Completion of the piles being
driven into the ground 15-18 feet
|
|
|
|
June 13, 2018
|
June 12, 2018
|
|
June 11, 2018
|
|
|
|
|
|
Side view of Boom Crane
at work on north side
|
Boom Crane driving pilings
|
Boom Crane at work on north side
|
|
South side clean and prep
|
|
June 7, 2018
|
June 6, 2018
|
|
June 6, 2018
|
|
|
|
|
|
North side prep work ready
for piling drives to begin
|
Preparation complete for pouring
of abutment wall – North side
|
Preparing for pouring of
abutment wall – North Side
|
|
Hold my beer – Watch this!
|
|
June 5, 2018
|
June 4, 2018
|
|
June 4, 2018
|
|
|
|
|
|
Preparing footing for abutment
wall North side
|
Cleaning continues around
project site
|
|
|
Sometimes it gets a
bit windy out here!
|
|
May 31, 2018
|
May 31, 2018
|
|
May 31, 2018
|
|
|
|
|
|
|
Bridge deck completely broken up
|
Jack hammering of original
bridge deck for removal
|
|
Jack hammering of original
bridge deck for removal
|
|
May 29, 2018
|
May 24, 2018
|
|
May 22, 2018
|
|
|
|
|
|
Installation of silt fence to prevent unwanted runoff from reaching
the creek |
Removal of bridge continues |
Bridge work removal started |
|
Bridge intact prior to removal |
|