This site only


Highway Department
2018 Construction Projects

County Bridge Projects

 

Road Name:

Somonauk Road Bridge

   Road District:

N/A

   Location: Bridge 0.25 miles South of US Route 30 in Hinckley, IL over Little Rock Creek
   Anticipated Start Date: May 21, 2018
   Anticipated Completion Date: All major work to be completed by 4:00pm August 31, 2018 to allow for road opening; Minor items are to be completed by 4:00pm, September 21, 2018
   Road Open to Traffic: NLT 4:00pm, August 31, 2018
   Contractor: Civil Constructors, Inc., Freeport, Illinois
   Contract Value: $993,826.37

   Improvements:

Removal and replacement of existing three span slab bridge with a new single span concrete deck on steel beams with integral abutments bridge along with necessary roadway approach work
   Traffic: Road to remain closed during construction
  PROGRESS UPDATES:                         

   
  (Please Remember to Refresh This Page for the Latest Update)

   

Date:

Topic:

 

August 31, 2018

Weekly Update -.PDF

 

Progress Photos:  Select the photos to see larger images



August 30, 2018

       
Leveling binder being placed
     
Bridge Complete!
     


August 30, 2018



August 30, 2018



August 28, 2018



August 28, 2018

Leveling binder being placed
Leveling binder being placed
Leveling binder being placed
Seeding of Right of Way
Application of pavement maring
Striping of new realigned roadway
Ditch stabilization underway
Seeding of Right of Way


August 27, 2018



August 24, 2018



August 24, 2018



August 23, 2018

Guardrail being installed
Preparing to install guardrail
Leveling binder being placed
Surface Course being placed
Guardrail being installed
Preparing to install guardrail
Aggregate Shoulders being placed
Surface Course being placed

August 23, 2018



August 15, 2018



August 15, 2018



August 14, 2018

Bridge rail being installed
Leveling binder being placed
Leveling binder being placed
Prime applied to realigned roadway
Bridge rail being installed
Leveling binder being placed
Leveling binder being placed
Prime applied to realigned roadway


 July 31, 2018 



July 31, 2018 



July 27, 2018



July 25, 2018

Forming deck
All beams have been set
First beam is set
Covering deck to allow it to cure to obtain proper strength
Pouring the deck
Rebar in place ready for deck pour
Tying rebar prior to deck pour


 July 13, 2018 



July 11, 2018 



July 11, 2018



July 9, 2018

Forming deck
All beams have been set
Realignment of roadway continues
First beam is set


July 9, 2018



July 9, 2018



July 9, 2018



July 5, 2018

Setting steel beams
Setting steel beams
Steel beams arriving at site
Abutments completed and forms stripped
Setting steel beams
Setting steel beams
Steel beams arriving at site
Abutments completed
and forms stripped

July 5, 2018

July 2, 2018
June 29, 2018
June 29, 2018
Preparing the base for new alignment of Somonauk Road
Pouring the Abutments.
Side view of Boom Crane
Boom Crane driving pilings
Preparing the base for new
alignment of Somonauk Road
Pouring the Abutments.
 Pouring of the Caps with concrete
Pouring of the Caps with concrete 

June 26, 2018

June 25, 2018
June 20, 2018
June 18, 2018
Reshaping Somonauk Road for better alignment to the bridge
Filling the piles with concrete after rebar has been set
Completion of the piles being driven into the ground 15-18 feet
Driving Piles
Reshaping Somonauk Road for
better alignment to the bridge
Filling the piles with concrete after rebar has been set
Completion of the piles being
driven into the ground 15-18 feet
Driving Piles

June 13, 2018

June 13, 2018
June 12, 2018
June 11, 2018
Side view of Boom Crane
Boom Crane driving pilings
Boom Crane at work on north side
South side clean and prep
Side view of Boom Crane
at work on north side
Boom Crane driving pilings
Boom Crane at work on north side
South side clean and prep

June 11, 2018

June 7, 2018
June 6, 2018
June 6, 2018
North side prep work ready
Preparation complete for pouring of abutment wall – North side
Preparing for pouring of
Teeterting backwards towards ditch
North side prep work ready
for piling drives to begin
 
Preparation complete for pouring
of abutment wall – North side
Preparing for pouring of
abutment wall – North Side
Hold my beer – Watch this!

June 6, 2018

June 5, 2018
June 4, 2018
June 4, 2018
Jack hammering of original bridge deck for removal
Cleaning continues around
Cleaning the channel
fallen barrades on road
Preparing footing for abutment
wall North side
Cleaning continues around
project site
Cleaning the channel
Sometimes it gets a
bit windy out here!

June 1, 2018

May 31, 2018
May 31, 2018
May 31, 2018
Old structure removal
Jack hammering of original bridge deck for removal
Jack hammering of original bridge deck for removal
Jack hammering of original bridge deck for removal
Old Structure Removed
Bridge deck completely broken up
Jack hammering of original
bridge deck for removal
Jack hammering of original
bridge deck for removal

May 30, 2018

May 29, 2018
May 24, 2018
May 22, 2018
Installation of silt fence to prevent unwanted runoff from reaching the creek
Bridge work removal started
bridge removal starting
bridge intact prior to removal
Installation of silt fence to prevent unwanted runoff from reaching
the creek
Removal of bridge continues
Bridge work removal started
Bridge intact prior to removal