Hot Mix Project
Road Name: |
Barber Greene Road |
Road District: |
N/A |
Village: |
N/A |
Location: |
Illinois Route 23 east to Peace Road |
Anticipated Start Date: |
June 18, 2018 |
Anticipated Completion Date: |
On or before October 26, 2018 |
Contractor: |
William Charles Construction Company, LLC |
Contract Value: |
$1,070,502.13 |
Improvements: |
Consist of removal and replacement of concrete curb and gutter, removal and replacement of a concrete barrier median, and placing a 1" lift of leveling binder (MM), IL-9.5FG, N50 and a 1 ½" lift of hot-mix
asphalt surface course Mix "C", N50 and other incidental work |
Traffic: |
Work will begin with shifting traffic to 1 lane each direction Monday, June 18th, followed by saw cutting and pipe removals and installation as the week progresses. Businesses along Barber Greene Road will still have access from Barber Greene Road during construction, however motorist should expect some minor delays as work is going on. |
|
PROGRESS UPDATES: |
|
|
(Please Remember to Refresh This Page for the Latest Update) |
|
|
|
|
|
|
|
Date: |
Topic: |
|
|
|
October 22, 2018 |
Weekly Update.PDF |
|
|
|