Hot Mix Project

 

Road Name:

Brickville Road, Twin Oaks Court, Twin Oaks Drive

   Road District:

Sycamore

   Village:

N/A

   Location: For Brickville Road - Motel Road to Whipple Road For Twin Oaks Subdivision (Court & Drive) – All  
   Anticipated Start Date: 7/5/2018
   Anticipated Completion Date: Project complete
   Contractor: Curran Contracting Company
   Contract Value: $173,038.95

   Improvements:

For Brickville Road - Consist of placing a 0.75" lift of leveling binder (MM), IL-9.5FG, N30 and a 1.5" lift of hot mix asphalt surface course, Mix "C", N30 and other incidental work; For Twin Oaks Subdivision - 1.5" lift of hot mix asphalt surface course, Mix "C", N30 and other incidental work
   Traffic: Will be completed under traffic with flagman providing temporary traffic control