Hot Mix Project

 

Road Name:

 

 

 

Coltonville Road
Rich Road
North First Street
Bethany Road

   Road District:

N/A

   Village:

N/A

   Location:

 

 

 

Coltonville Road – From N. First Street to Illinois Route 23
Rich Road – From Glidden Road to N. First Street
North First Street – At intersection of Rich/Coltonville Roads
Bethany Road – From YMCA to Illinois Route 23
   Anticipated Start Date: Not before June 11, 2018
   Anticipated Completion Date: This project is complete.
   Contractor: William Charles Construction Company, LLC
   Contract Value: $890,771.85

Improvements:

 

  

 

 

 

 

Consist of placing 1 ¾" and 1 ½" lifts of hot mix asphalt surface course
Mix "C" N50 and other incidental work on Rich Road and Coltonville
Road; placing a 1" lift of leveling binder (MM), IL-9.5FG, N50 and a 1 ½"
lift of hot-mix asphalt surface course Mix "C", N50 and other incidental
work on North First Street; placing a 0.75" lift of leveling binder (MM),
IL-9.5FG, N50 and 1 ½" lift of hot mix asphalt surface course, mix "C",
N50 and other incidental work on Coltonville Road and Bethany Road
on the northwest side of DeKalb, Illinois
   Traffic: Will be completed under traffic with flagman providing temporary traffic control