Hot Mix Project

 

   Final Update: 10/23/2018  
   Road Name: Gurler Road
   Road District: DeKalb
   Village: N/A
   Location: DeKalb City Limits to South First Street
   Anticipated Start Date: August 1, 2018
   Anticipated Completion Date: Completed on August 15, 2018
   Contractor: Curran Contracting Company
   Contract Value: $99,361.16 – Final Cost (estimate -$100,096.45)

Improvements:

Consist of placing a 0.75" lift of leveling binder (MM), IL-9.5FG, N30 and a 1.25" lift of hot mix asphalt surface course, Mix "C", N30 and other incidental work
   Traffic: Will be completed under traffic with flagman providing temporary traffic control