Hot Mix Project
Final Update: 10/23/2018 |
|
Road Name: |
Gurler Road |
Road District: |
DeKalb |
Village: |
N/A |
Location: |
Bridge over the south branch of the Kishwaukee River west to Anderland Road |
Anticipated Start Date: |
August 1, 2018 |
Anticipated Completion Date: |
Completed on August 13, 2018 |
Contractor: |
Curran Contracting Company |
Contract Value: |
$233,886.92 – Final Cost (estimate: $244,652.97) |
Improvements: |
Consist of placing a 0.75" lift of leveling binder (MM), IL-9.5FG, N30 and a 1.25" lift of hot mix asphalt surface course, Mix "C", N30 and other incidental work |
Traffic: |
Will be completed under traffic with flagman providing temporary traffic control |
|