Hot Mix Project
Road Name: |
Oakview Lane |
Road District: |
Genoa |
Village: |
N/A |
Location: |
All |
Anticipated Start Date: |
To be determined |
Anticipated Completion Date: |
On or before September 28, 2018 |
Contractor: |
Curran Contracting Company |
Contract Value: |
$35,945.12 |
Improvements: |
Consist of placing a 1.25" lift of hot mix asphalt surface course, Mix "C", N30 and other incidental work |
Traffic: |
Will be completed under traffic with flagman providing temporary traffic control |
|