Chicago Road Reclamite Project
Road Name: |
Chicago Road |
Road District: |
N/A |
Location: |
Maplewood Road east to Somonauk Road
|
Anticipated Start Date: |
May 31, 2016 |
Anticipated Completion Date: |
June 3, 2016 - Project Completed |
Contractor: |
Corrective Asphalt Materials |
Contract Value: |
$61,425.54 |
Improvements:
|
Rejuvenator – Reclamite, to be applied at a rate of 0.05 to 0.10 gallons per square yard when mixed with water. After penetration in surface, a coating of dry sand to be applied on surface in sufficient amount to protect the traveling public as determined by the Resident Engineer |
Traffic: |
Road to remain open to one way traffic during application |
|