Road Name: |
Melms Road |
Road District: |
Genoa |
Location: |
0.3 mile West of New Lebanon Road over Coon Creek
|
Anticipated Start Date: |
N/A |
Anticipated Completion Date: |
Road Open to Traffic by November 22, 2016
All work to be completed by December 8, 2016 |
Contractor: |
Martin & Company Excavating |
Contract Value: |
$641,336.18 |
Improvements: |
Removal and replacement of existing three span bridge with a three span precast prestressed box beam bridge. Width of 30" between rails and other incidental work |
Traffic: |
Road to remain closed during construction |