Township Paving Project - DeKalb
Road Name: |
Bethany Road
|
Road District: |
DeKalb |
Location: |
825 Feet north of City Limits of DeKalb to Glidden Road
|
Anticipated Start Date: |
May 16, 2016 |
Anticipated Completion Date: |
October 14, 2016 --Project Completed May 31, 2016 |
Contractor: |
Peter Baker & Son Company |
Contract Value: |
$338,515.01 |
Improvements:
|
1" Leveling Binder, N30 and 2" Hot-Mix Asphalt Surface Course;
10' aggregate shoulders; commercial and private entrances paved to
right-of-way; field entrances paved 3' then placed aggregate to right-of- way and other incidental work. |
Traffic: |
Road to remain open to one way traffic during construction |
|