Franklin Paving Project
Road Name: |
Unincorporated Fairdale Streets |
Road District: |
Franklin |
Location: |
Fairdale
|
Anticipated Start Date: |
N/A |
Anticipated Completion Date: |
August 16, 2016 |
Contractor: |
Universal Asphalt & Excavating, Inc. |
Contract Value: |
$107,625.51 |
Improvements: |
2" lift on Main Street and 1.25" lift on hot-mix asphalt surface mix C, N30 and other incidental work on all roads – 1.13 miles total |
Traffic: |
Roads to remain open to one-way traffic during construction |
|