Township Paving Project - Genoa
Road Name: |
Briody Way – Madison Road east to end of cul-de-sac
Northwood Drive– North State Road, east, south, west to North State
Road |
Road District: |
Genoa |
Location: |
See Above
|
Anticipated Start Date: |
May 5, 2016 |
Anticipated Completion Date: |
June 3, 2016 --Project Completed May 31, 2016 |
Contractor: |
Peter Baker & Son Company |
Contract Value: |
$62,188.56 |
Improvements:
|
1 1/2" Hot-Mix Asphalt Surface Course; 3' Aggregate shoulders;
private entrances paved back to the right-of-way; field entrances
3' paved surface then aggregate shoulders to right-of-way and other
incidental work |
Traffic: |
Road to remain open to one way traffic during application |
|