Construction Project - Cortland Township Seal Coat
Road Name: |
Gurler Road – Chase Road east to Hinckley Road
Pritchard Road – Illinois Route 38 south to Pierce Township Line
Fenstermaker Road – Pleasant Street north to Bethany
Bethany Road – East Branch Kishwaukee River Bridge east to Quigley
Road
Quigley Road – Airport Road east to Lovelle Road
Larson Road – Barber Greene Road north to Illinois Route 64 (Double Seal) then single seal from Illinois Route 64 north to Old State Road -Double Seal
--then sigle seal from Illinois Route 64 north to Old State Road
|
Road District: |
Cortland |
Location: |
*See Above
|
Anticipated Start Date: |
Week of July 4th |
Anticipated Completion Date: |
August 12, 2016 |
Contractor: |
Civil Constructors, Inc. |
Contract Value: |
$155,929.10 |
Improvements:
|
Placement of bituminous material (oil) Seal Coat of HFE-150 at a rate of
.40 gallons per square yard and seal coat aggregate placed at a rate of
26 pounds per square yard |
Traffic: |
If contractor elects to seal entire road at once, and if approved by
the County Engineer, road may be closed to through traffic on a rolling
closure basis |
|