Construction Project - Mayfield Seal Coat
Road Name:
|
North Grove Road – Church Road east to Five Points Road
East Clare Road – Clare Road east and north to Old State Road
Aldrich Road – Double Seal – Ault Road east to Johnson Road |
Road District: |
Mayfield |
Location: |
See Above
|
Anticipated Start Date: |
Week of July 4th |
Anticipated Completion Date: |
August 12, 2016 |
Contractor: |
Civil Constructors, Inc. |
Contract Value: |
$63,616.20 |
Improvements:
|
Placement of bituminous material (oil) Seal Coat of HFE-150 at a rate of
.40 gallons per square yard and seal coat aggregate placed at a rate of
26 pounds per square yard |
Traffic: |
If contractor elects to seal entire road at once, and if approved by
the County Engineer, road may be closed to through traffic on a rolling
closure basis |
|