DEKALB COUNTY PUBLIC BUILDING COMMISSION
A MUNICIPAL CORPORATION AND BODY POLITIC ORGANIZED PURSUANT TO THE “PUBLIC
BUILDING COMMISSION ACT.” ILLINOIS REVISED STATUTES 1977 CHAPTER 85, SECTIONS
1031 THROUGH 1054 CHAPTER 85, SECTIONS 1031 THROUGH 1054 AND CURRENTLY UNDER
ILLINOIS COMPILED STATUTES 50 ILCS 20/1 et seq.
MEETING OF THURSDAY, NOVEMBER 6, 2008
A regular meeting of the Board of Commissioners of the DeKalb County Public
Building Commission (hereinafter “Commission”) was held Thursday, November 6,
2008, at 8:30 A.M. in The Multi-Purpose Room of the DeKalb County Health
Department Campus, pursuant to written notice to each Commissioner as required
by the By-Laws.
ROLL CALL
The meeting was called to order by Chairman Robert Hutcheson at 8:30 A.M.
Commissioners present were Chairman Hutcheson, Dr. Richard Baker, Mr. Matt
Swanson, and Mr. George Daugherty. Mr. Beryl Smith arrived at 8:38 A.M. Also
present were Mr. Gary Hanson, Mr. Jim Scheffers, Mr. Matt Bickel and Mr. Jeff
Burandt of Wold Architects & Engineering, Mr. Brian Kerner of Burnidge Cassell
Associates and Secretary Mary Simons.
APPROVAL OF MINUTES
Mr. Daugherty made a motion to approve the minutes of the meeting held on
Tuesday, October 7, 2008. The motion was seconded by Mr. Swanson. The motion
carried unanimously by a voice vote.
APPROVAL OF AGENDA
Mr. Swanson made a motion to approve the minutes as presented. Mr. Daugherty
seconded the motion. The motion carried unanimously by a voice vote.
COMMUNITY OUTREACH BUILDING-Project Status
Mr. Jeff Burandt reported that the Contractor has given him the date of
Wednesday, November 13, 2008 for completion. However, that does not include
their requirements to touch up the building or to complete all the punch list
items that have been identified by Wold and will be started next week. Our goal
is to have all the contractors out of the building before the furniture is
delivered. Dr. Baker asked what kind of items are on the punch list. Mr. Bickell
stated that there are some major items but they are mostly incomplete items such
as the carpet. He added that their biggest task will be the final cleaning,
however, they have scheduled a full time cleaning crew beginning on Monday,
November 10, 2008. Mr. Hanson stated that the tentative move in dates are as
follows: December 18, 2008 will be the Information Management Office and
Facilities Management. The Veterans on January 6, 2009, The Mental Health
Department and the Regional Office of Education on January 7, 2009 and the Home
Care Offices on January 13, 2009. Mr. Hanson said that it is anticipated that
these are the scheduled dates but they are subject to change due to a possible
delay in the delivery of the emergency generator. He added that the emergency
generator is scheduled for delivery on approximately December 10th or 12th.
CHANGE ORDERS
Mr. Bickel distributed the change orders (Attached as Exhibit #1) and described
them as follows: Change Order #14.1 is for the cost associated with relocating a
fire strobe in Conference Room West for a cost of $260.00. 14.2 is the cost
associated with providing duct smoke detectors and wiring them to duct smoke
dampers which was not included in the electrical drawings at a cost of
$11,050.00. 14.3 is for the cost associated with relocating the audio/visual
system for the Educational Center which is a pending item. Mr. Swanson asked why
item 14.2 was omitted from the electrical drawings. Mr. Bickel explained that
the Mechanical Contractor failed to cross reference the mechanical drawings
where the physical dampers themselves are part of the mechanical system and the
cost of the wiring for them did not show up on the electrical drawings. Dr.
Baker asked why they did not show up on the electrical drawings. Mr. Bickel
responded that it was an oversight. Mr. Smith expressed his disappointment
regarding the number of change orders that were not included on the original
drawings or schematics. Mr. Swanson concurred. The consensus of the
Commissioners is that some of the cost for this oversight should be borne by the
architectural firm. Dr. Baker asked if Wold did the actual electrical drawings
for the project. Mr. Bickel responded that the drawings were actually done by
Gage Consulting Engineers. Dr. Baker asked if this situation has been brought to
the attention of Gage. Mr. Bickel responded affirmatively. Mr. Hanson stated
that this item needs to be approved today but perhaps at a later date it could
be determined who will be responsible for paying certain portions of this cost.
Mr. Bikel stated that the total for Change Order #14 is $11,310.00 plus item
14.3 which is pending. Mr. Bickel stated that Change Order # 15.1 is for the
cost of revising the fire suppression system in the server room in the amount of
$3,363.00. Mr. Bickel stated that Change Order #16.1 is for costs associated
with the painting and vinyl flooring at the front reception area of Room B-112
which is the future office space at a cost of $3,557.40 and item 16.2 which is
the cost associated with revising the roofing to accommodate a rerouted vent at
a cost of of $236.50 for a total cost for Change Order #16 at $3,703.90. Mr.
Bickel stated that Change Order #17.1 is for providing a sink in the Home Care
break room in the amount of $437.59 and item 17.2 is for providing a
refrigerator water line in Break Room #A147 which is a pending cost. The total
for Change Order #17 is $437.59 plus item #17.2. Dr. Baker moved to approve the
change orders and Mr. Smith seconded the motion. The motion carried unanimously
by a voice vote.
PAY REQUESTS
Mr. Hanson distributed Exhibit #2 containing pages A through E-8. Mr. Bickel
presented Pay Request #11 from Rockford Structures in the amount of $249,002.85,
from G’sR Plumbing in the amount of $26,038.00 and Mascal Electric in the amount
of $55,589,00 for a total of $330,630. (These requests are shown on Page C of
Exhibit #2 attached) Mr. Bickel stated that Automatic Fire Systems and MG
Mechanical did not submit pay requests this month. Dr. Baker made a motion to
approve the pay requests as presented. Mr. Swanson seconded the motion. The
motion carried unanimously by a voice vote.
UPDATE OF 2008 PROJECTS (Attached as Page “D” of Exhibit 1)
Mr. Brian Kerner spoke about the PSB Boiler/Water Heater Replacement Project.
Mr. Kerner stated that the gas regulators have been replaced, all the insulation
is in except for around the area of the gas regulators and the concrete pads
have been installed. Mr. Kerner added that except for some fine tuning, which
will be done over the next several days, the project is complete.
Mr. Hanson said the other project to be completed is the Dispatch Room in the
Public Safety Building which is item #10 on the project list. Mr. Scheffers
stated that we are waiting for the arrival of the air conditioning unit which is
taking approximately twelve weeks to complete because it is essentially a custom
built unit. Mr. Scheffers added that the unit is scheduled to be shipped on
November 25, 2008.
Dr. Baker said he has some questions regarding item #5 for the Treasurer’s
project. He added that he has spoken with Christine Johnson and she stated this
was a two year project. Dr. Baker said he has seen the final plan and had made
some suggested changes and asked if anyone had seen the “final, final” plan. Dr.
Baker requested that a set of the “final, final” plans be given to the
Commissioners for review. Mr. Hanson stated that he does not have a set of the
“final, final” plans. Ms. Simons said she does not have a set either but is
aware that the Treasurer was working with Swedberg Construction on some slight
changes to the plans. Dr. Baker stated that he had a number of comments and
suggestions regarding the plan he saw and is interest in what changes of his may
have been incorporated into the Treasurer’s “final, final” plan. Dr. Baker
requested that the Treasurer attend a meeting and present her changes since this
is a 2009 project. Mr. Hanson stated that he was hopeful that the furniture
reconfiguration portion of the project could be done this year. Dr. Baker stated
again that he had a number of concerns regarding her plans and was wondering if
she took those and changed anything. Dr. Baker said he felt uncomfortable with
her plan in regard to functionality in the area of construction a wall with
“teller-like” window openings. Dr. Baker then asked if the $100,000 shown in the
Circuit Clerk’s 2nd floor project has been approved. Mr. Hanson responded that
it would be included in the budget approval today and the County Board will
approve it in two weeks. He added that we are approving the $100,000 but have no
idea when the project will be complete. Ms. Simons responded that the project is
underway and construction has begun on the counter and public areas. She added
that the tile floor in the public entry area has been installed and the chairs
that were ordered for the staff have arrived. Ms. Simons added that the Circuit
Clerk has informed us that the project is being done one area at a time and the
design for the staff area will be completed shortly at which time the furniture
will be ordered. Ms. Simons explained that the Circuit Clerk felt there were
some flaws in the design for the reconfiguration of her first floor office and
to avoid those mistakes she prefers to proceed cautiously and complete the
reconfiguration of her second floor offices in phases. Dr. Baker said that as he
looks at the project report he has no idea where the project is in terms of
progress toward completion and yet is into next years budget. Mr. Hanson
explained that at this point we don’t know what the progress is either. He added
that most projects in which the PBC is involved, the people want us to work with
them but in this case the Circuit Clerk wants to do this on her own. He added
however, it has been established with Maureen that the PBC can only fund up to
$100,000. Dr. Baker asked if this is a lapsing project or do we have to renew
it. Mr. Hanson stated that it needs to be re-appropriated. A lengthy discussion
took place regarding how much control the PBC has in relation to the statutory
authority of the elected officeholders. Mr. Hanson pointed out that our job is
to bring the players together and assist them but the PBC’s control is the
appropriation. He added that the officeholder has the autonomy to operate their
office as they see fit. Dr. Baker stated that he would like some communication,
which could be in person or in written form, from Maureen and Christine
regarding their vision for their projects, where they are and when they expect
to complete them. It was established that the County Board approves the projects
and the funding for them but the authorization to spend the money will be
brought before the Commission. Dr. Baker made a motion requesting information
from the Circuit Clerk’s office and the Treasurer’s office on these two capital
projects and the information to include where they are now and what their vision
is for their projects. Mr. Swanson seconded the motion. The motion was
unanimously approved by a voice vote.
2009 BUDGET (Exhibit #1, Pages “E-1 through E-8)
Mr. Swanson made a motion to table action on the PBC Budget until it is approved
by the County Board. Mr. Smith seconded the motion.
A lengthy discussion took place regarding the sequence for the approval of the
PBC Budget and the ability for the Commissioners to provide input prior to
approval by the County Board. Mr. Hanson pointed out that the Commissioners had
that ability to provide input regarding the Capital portion when it was provided
to them in September, however, at this point it is too late for input to the
County Board. Mr. Hanson explained the projects given to the Commission by the
County Board are contained on pages E-4, E-5, and E-6. He added that the
Commissioners do approve their own operating budget. The Chairman called for a
vote on the motion to table. The motion carried unanimously by a voice vote.
NEW/OLD BUSINESS
Mr. Swanson inquired about the two concrete projects that were being done last
week using two different contractors. He explained that one of the projects was
done at the Courthouse and the second one at the Legislative Center and asked
where the projects came from and were the projects put out for bid. Mr.
Scheffers responded that there is a $10,000 line item in the Facilities budget
for replacement of broken sidewalks and concrete repair. Mr. Swanson asked if
those two projects should have been the responsibility of the PBC. Mr. Hanson
stated that the PBC contracts with the County Facilities Department to do the
maintenance projects. Mr. Scheffers stated that the repairs made at the
Courthouse were part of his line item. Mr. Hanson explained that the project was
at the Administration Building and was paid for by the County from the Tort Fund
to reduce the risk of someone being injured from falling on a broken curb and
sidewalk. Mr. Hanson added that neither project qualified under the $20,000
limit for competitive bidding. Mr. Swanson stated that the PBC By-Laws states
that any project more than $2,500. Must be competitively bid. Mr. Hanson
explained that state law provides for the amount to be $20,000. Mr. Swanson
stated that Article 7, Section 1 of the PBC By-Laws provides for the amount to
be $2,500. Dr. Baker suggested that perhaps the By-Laws should be revised. Mr.
Swanson also stated that it appears the By-Laws, with a catch all phrase,
adequately provides for the duties of the Secretary and the Treasurer of the
PBC. Dr. Baker stated that the duties of the Secretary have been expanded quite
a bit and the By-Laws are very outdated. The Chairman asked if someone should be
directed to review them. Mr. Hanson responded that he and Ms. Simons were given
that direction at the last meeting but it has not been done yet. Dr. Baker make
a motion to amend the By -Laws with regard to project bidding by the next
meeting in accordance with the provisions in the State law and the other items
needing attention be addressed in the near term. The motion was seconded by Mr.
Daugherty. The motion carried unanimously by a voice vote.
The next meeting will be held on Tuesday, December 2, 2008 at 8:30 A.M. in
Conference Room East.
ADJOURNMENT
A motion was made by Mr. Daugherty to adjourn the meeting. The motion was
seconded by Dr. Baker. The motion carried unanimously by a voice vote. Meeting
adjourned at 10:20 A.M.
__________________________
Robert Hutcheson, Chairman
____________________________
Mary G. Simons, Secretary
Commissioner |
Expiration of Term |
Office |
Original Appointment |
|
|
|
|
Mr. Robert Hutcheson |
September 30, 2009 |
Chairman |
January 16, 1991 |
Mr. Beryl Smith |
December 01, 2010 |
Vice Chairman
|
September 30, 2000 |
Dr. Richard Baker |
September 30, 2011 |
|
September 30, 2005 |
Mr. Matt Swanson |
September 30, 2012
|
|
September 19, 2007 |
Mr. George Daugherty |
September 30, 2013 |
|
September 30, 2008 |
|
|
|
|
Non-Commissioner: |
|
|
|
|
|
|
|
Ms. Mary G. Simons |
September 30, 2008 |
Secretary |
March 7, 2000 |
Mr. Gary H. Hanson |
September 30, 2008 |
Treasurer
|
February 18, 1984
|
|
|
|
|
|
|
|
|
|